Residual contamination liquidation in former military and indrustial areas
Client: Keskkonnateabe Keskus
Contract Period: March 2013 – March 2015
Contract Cost: 3 282 630 EUR (ex VAT)
Capacity Information:
- Transfer of contaminated soil that has exceeded the limit values (see Regulation No. 38 of the Minister of the Environment of August 11, 2010 “Limited values for the content of hazardous substances in soil” (RTL 18.08.2010, 57, 373)), subsequent processing or disposal in a designated landfill.
- Demolition of facilities subject to liquidation in polluted areas and handling of generated waste (reuse or disposal).
- Elimination of high vegetation in the area with polluted soil (if necessary).
- Improvement of cleaned areas, and restoration of their good condition.
- Operational implementation of the monitoring system for studies following pollution elimination works.
The general goal of the project was to localize the source of residual pollution that threatens groundwater, prevent environmental pollution, and eliminate residual pollution.