Railway reconstruction
Client: EVR Infra AS
Construction Period: October 2009 – June 2010
Construction Cost:: 5 780 480 EEK / 369 440 EUR (ex VAT)
Capacity Information:
- Repair of roads by dismantling the old road grating and installing a new road grating on reinforced concrete sleepers (1000m.).
- Improvement of road geometry filling machine (16,000m.).
- Replacement of wooden sleepers (4,450 pcs.).