General construction of the EstLink2 converter station
Client: Siemens Osakeyhtiö Estonian Branch
Construction Period: January 2012- August 2012
Construction Cost: 3 295 000 EUR (ex VAT)
Capacity Information:
- General construction of the converter station, including foundations, buildings, site constructions, etc.
- Transmission capacity 650MW.